现代堆石坝技术进展

出版社:中国水利水电出版社
出版日期:2009-10-01
ISBN:9787508468679
作者:贾金生

章节摘录

  The material for the first 10 layers of the em-bankment is processed with conventional earth-work construction machinery. The excavated ma-terial brought from the borrow areas is transpor-ted to the processing yard, then spread with abulldozer in layers generally 150 mm thick andsprinkled with water. Most of the larger lumpsbreak down to small size in this processing ofspreading. Finally tamping - foot roller or bull-dozer is employed to roll over the fill material byseveral passes till the percentage of lumps is re-duced to 12% to 13%. Material coarser than 10mm in size is catergorised as lumps. The numberof passes for various layers varies hetween 15 and 22. Water is sprayed over the processed layer and the material is then pushed by dozer blade into a stockpile. While pushing, the dozer blade inevi-tably excavate some material from ground which is drier. Water is added to the piled - up materialand the material worked with the loader buck- et. The water content of the material is broughtto within zero to +3% of the optimum watercontent. 3. 2. 2 Processing by agricuLtural rotavatorThe material for the last 12 layers of the em-bankment is processed with agricultural rotava- tor. The object of using the rotavator is to reducethe material processing effort.The excavated material is spread in 150 mm thick layers by the bulldozer blade. The material is then loosened by the dozer rippers and water is sprinkled over the surface. The processing is then performed by therotavator, with more water being sprinkled if required.ln every pass, the rotavator penetrates 20 to 30 mm into the layer while cutting and pul- verizing the lumps. Generally 6 passes of the ro- tavator i.s required to achieve full penetration of 150 mm into the layer. When full penetraiion is achieved, the proportion of lumps in the materi- al is 15% to 25% and the maximum size of the lumps is about 100 mm.The processing of the material is continued with further passes of the ratavator. The proportion of lumps is reduced to about 12% after 8 to 18 passes. The maximum size of the lumps is a7oout 50 mm. The processed materials is stockpiled by aloader, water is added to the stockpile as re-quired to increase the water content of the pro-cessed material. Mixing of water is achieved byworking the material with the front - end loader.3. 3 Construction o f trial embankmentThe processed fill material stockpile in the pro-cessing area is transported to the trail embank-ment by dumps.Since the grader has brokendown at the early stage, bulldozer is deployedfor spreading and leveling.ln this case, thespreading thickness is not uniform and the com-paction thickness varied from 100 to 190 mm.  A self - propelled single - drum tamping - footvibratory roller with a static weight of 10. 2 tonswas used for compaction. As the fill material issilt, vibration is not used for compaction.The tamping - foot roller operates at a speed of 4 km/hour to achieve a compacted dry density of 97%of the maximum standard Proctor dry density. Generally the compacted surface is hard andhomogeneous after 6 passes of the roller, ex-pects for a few wet spots during Stage 1 wherethe moisture is much above the optimum due to lack of suitable water - mixing equipment. Thi.sproblem does not occur during Stage 2 because ofthe uniform mixing of water by the rotava-tor. Sometimes the compacted surface is undulat- ing due to the uneven spreading and poor levelingof material by the bulldozer. The proportion of lumps in the compacted fillis found to be about 8% to 9% compared withthe range of 12% to 13% before pacement and compaction. This reduction in the lumps contentoccurs during haulage of the material from theproce.ssing area to the embankment, spreadingof the material by the bulldozer and compaction by the tamping - foot roller.  ……

书籍目录

Table of ContentsPre f aceTheme l : Project Introduction , History, Case and Experrence o f Rock f ill DamReview and Suggestions on CFRD ConstructionZhao Zengkai (China)Deformation Control of the 200 m High Hongjiadu Concrete Faced Rockfill DamYang Zeyan, Jiang Guocheng (China)Repair of CFRDs in the Dry and Underwater:Salt Springs and TurimiquireSequera R , Perazzo P , Scuero A , Vaschetti G (Venezuela)Mazar CFRD Dam: Main Features on Design and ConstructionMarcelo G Costa, F f ren Estrella , ManoeL S Freitas J r (Ecuador)Technical Progress of CFRD Constructed on Deep AlluviumXu Zeping (China)Construction of Lianghekou Earth-Core Rockfill Damon Yalong River Wu Shiyong, Shen Manbin, Xi Zhiyong (China)Design and Construction Techniques for a Safe Planning and Execution of High CFRDsBayardo Materon (Brazil)A Case - Study of Cua - Dat CFRD in VietnamGiang Pham Hong, Michel Hotakhanh (Vietn:am)The Asphalt Core Embankment Dam: A Very Competitive AlternativeWang Weibiao, Kaare Hoeg (China)Nam Ngum 2 Hydroelectric Power Project Encountered Technical and EconomicalChallengesPratoomkhuan Ngarmsirilertsgoon, SakoLkiat Puangpatcharakul (Laos)Gibe III: A Zigzag Geomembrane Core for a 50 m High Rockfill Cofferdam in EthiopiaPietrangeli G , Pietrangeli A , Scuero A , Vaschetti G (Italy)Rockfill Dam Engineering Practice in Huizhou Pumped Storage Power StationL/u Yajun , Zhang Peng (China)Construction and First Impounding of the Tokuyama DamHino Koji, Soda Hideki (Japan)Dam Safety & Water Resources Planning Project in Sri Lanka - SpecialConsideration on Rockfill DamsSudahrma Elakanda , Madusha Chandrasekera (Sr/ Lanka)Theme 2 : Design and AnalysisAchievements and New Considerations on Re-constructing of Diversion Tunnelinto Spiltway Tunnel in High Earth and Rockfilled DamsGuo Jun, Gao Jizhang (China)Spillway Hydraulic Issues in Rebuilding Embankment Dams - Experiences fromVattenfall's Dam - Safety Program James Yang, MaLte Cederstrom (Sweden)Adaptability of Slab Joint Waterstop to Very High CFRD Hao Jutao, Lu Yihui, Jia Jinsheng, Du Zhenkun, Dou Tiesheng (China)Design of Concrete Face Slab for 182 m High NN2 CFRD Aphichat S , Pastsakorn K , Weerayot C , Rawee S (Thailand)Design and Verification Analysis on the Maopingxi Asphaltic Concrete CoreWall Embankment Dam of the Three Gorges ProjectXu Tangjin, Yu Shengriang, Yan Shuanghong (China)Mesh Generation fOr 3-D Dynamic Analysis of Fill DarnIk -Soo Ha, Byung - Hyun Oh , Wan - Ho Lee (RepubLic o f Korea)Analysis on Engineering and Technical Characteristics of ShuangjiangkouHydropower Proj ectChen Bang f u (China)Design Considerations of a High Rockfi/l Dam Nam Ngum 2 CFRD, Lao PDRRuedi Straubaar, Eva van Gunsteren, Stephen Motl (Switzertartd)Finite Element Analysis of a Super High Earth Core Rockfitt Dam on Deep Overburden Pan J iajun , Wang Mingyuan, Xu Han (China)The Desjararstifla Dam: Measures in the Foundation to Mitigate Adverse effectsof Faults & Lineaments PaLmi R Palmason, Fj61a G Sigtryggsdottir (IceLand)Study of Seepage Control Characteristics of JinchuanConcrete Faced Rockfill Dam on Dadu River Rong Guan, Pan Shaohua (Ch/na)FEM Analysis of a Concrete Faced Rockfill DamGerd-Jan Schreppers, Giovanna Lilliu (Netherlands)A New Method for Estimatrng the Deformabrlity Modulus of PlasticConcrete-gotvand Dam Experience, Southwest IranHeidarzadeh M , Sadr -Lahijani SM , Niroomand H (Iran)Numerical Analysrs on Asphalt Concrete Core Rockfill Dam Using Elasto-PlasticCouple Constitutive ModelZhu Sheng, She Yapeng (China)Irape Dam - Stress and Strain: Numerical Previsions and Measurement ResultsAler Martins Calcina, Jander de Faria Leitao, Reginaldo Araujo Machado (Brazil)

作者简介

现代堆石坝技术进展(2009 英文版),ISBN:9787508468679,作者:贾金生,等 编

图书封面


 现代堆石坝技术进展下载



发布书评

 
 


 

外国儿童文学,篆刻,百科,生物科学,科普,初中通用,育儿亲子,美容护肤PDF图书下载,。 零度图书网 

零度图书网 @ 2024